Asian Paints Smartcare waterproofing methodology & work details
USING ASIAN PAINT’S SMARTCARE PU MAGNUM US
& SMARTCARE PU INSULATOR & Damp-proof Ultra + Screed
1.0 MATERIALS SPECIFICATION REFERENCE |
This Method Statement is to be read in conjunction
with relevant documentation. 1.
Please
refer to PIS of the relevant products mentioned in this method Statement 2. Safety Data Sheets 3.
Relevant
Application Instructions if any from the Manufacturer |
2.0 MATERIAL REQUIREMENTS |
The materials needed for to complete the tasks set
forth in this method statement are: 1.
Smartcare
PU Ultron 2.
Smartcare
Epoxy Primer 3.
Smartcare
PU Insulator 4.
Smartcare
PU Magnum 5.
Closed
Cell Backer Rods for Joints and deep cracks 6.
Smartcare
Hybrid PU sealant 7.
SmartCare
GP Grout/Micro Concrete 8.
Smartcare
Repair Polymer 9.
SC
Vitalia Neo 10. Silica Sand: 0.3 to 2 mm in grain size 11. 60 Gsm non-woven geotextile for crack & change
of plane treatment 12. 150-200 Gsm Geotextile fabric to use as a separation
layer |
3.0 GENERAL APPLICATION PARAMETERS |
|
Condition |
Limitation |
Ambient
Temperature |
>
5 to 40 |
Humidity |
<
80% |
Substrate
Moisture level |
Moisture Level for Smartcare PU Magnum US
application to be less than 4% |
Minimum
Compressive Strength of Substrate |
20 MPa |
Pot
Life at 25 C |
Approx. 25 minutes |
4.0 MANDATORY APPLICATION TOOLS AND
SERVICES |
The applicator shall have at the minimum, the
following tools for suitable application of Smartcare PU Ultron. §
Airless
Proportionating 1 Component Spray Machine, Plural machine §
High
Pressure Water Jetting [> 160 bars] §
Hammer
/ Jack hammer §
Chisels
§
Grinders
and accessories §
Wire
brush & Other Cleaning tools §
Air
blower §
Jiffy
Mixer [handheld] §
Roller
/ Brush / Squeeze §
Substrate
Moisture Meter / Thermometer / Humidity Gauge §
Safety
Helmet / Vest Reflective Jackets / Safety Shoes §
Rubber
Hand Gloves / Mask §
Wet
film thickness gauge §
Mechanical
Stirrer §
Graco
XP2 §
PPE’s
for personnel SERVICES: Main Civil Contractor shall hand over to the
Specialist waterproofing applicator, the substrate in a cleaned condition
free from water, grease, oil, surface defects, debris, dirt, or any other
depositions. The main civil contractor shall also provide necessary lifting
arrangements for any equipment / materials and shall also provide a covered
storage area for materials. The main Civil Contractor / Owner shall provide
water and electricity, at site at no charge. |
5.0 KEY SITE REQUIREMENTS |
WORK
SCHEDULE: Specific requirements for Schedule to be agreed upon
mutually between the specialist waterproofing applicator and the main civil
contractor so as to meet the overall project schedule. SITE
SAFETY REQUIREMENTS: The main civil contractor shall make provisions for
the following safety accessories / appurtenances: §
Eye
Wash station §
First
Aid Station §
Respirators
for Special Applications §
Protective
Aprons PERSONNEL
REQUIREMENTS: Applicator Qualifications: Shall be trained and approved by the manufacturer
for the application of the system specified. The applicator firm should have
at least 10 years’ experience in successful skilled application of Polyurethane
based waterproofing systems with airless spray machine. Supervisor Qualifications: Shall be trained experienced and capable of
handling spray applied waterproofing systems, should have supervised cold application
of Polyurethane based waterproofing systems with airless spray machine /
Roller / Brush application, for at least 2 years. Technician Qualifications: Should be trained by the manufacturer for the
application of the system specified. |
6.0 METHOD OUTLINE |
The application of Smartcare PU Ultron should follow the general
procedure as outlined in this section: 1.
Surface Preparation 2.
Repair of the substrate to
provide an even / stable substrate 3.
Repair of Surface Cracks /
Construction Joints 4.
Repair of Moving Cracks if any 5.
Treatment of Horizontal /
Vertical and Vertical / Vertical Interfaces using Smartcare PU Sealant 6.
Application of the Smartcare PU ultron 7.
Termination 8.
Curing 9.
Protection System |
7.0 DETAILED METHODOLOGY |
Pre-Pond Test:
Injection
Grouting, if required:
SURFACE
PREPARATION: ·
Prior
to waterproofing installation, arrange a visit to project site with
representative from the manufacturer. Representative shall inspect and
certify that concrete surfaces are in acceptable condition to receive
waterproofing treatment. ·
Surface
to be waterproofed will be dry concrete, cementitious surface, tiled surface
or dry treated shall be clean, sound and free of all contaminants which may
interfere with adhesion or proper curing of the membrane. If release agents
are present, they must be removed prior to the application of Smartcare PU
Magnum US. ·
Concrete
substrate should be light steel trowelled followed by a fine hair broom or
equivalent finish achieving a slightly rough concrete surface profile similar
to that recommended in ICRI CSP 2-5.
Concrete surface shall be free of voids, exposed aggregate areas, honey
combs, splatters, ridges, fins and other projections or depressions which
preclude a smooth and level surface. ·
All
reinforcing, including cut off rebar, shall be covered by a minimum of 20 mm
of concrete, epoxy or approved repair mortar. ·
Concrete
masonry unit construction may receive a plaster coat of acceptable
cementitious coating approved by manufacturer. All CMU walls must have all
joints solid grouted and struck flush with no voids. ·
For
horizontal applications, follow good drainage practice to permit unimpeded
water flow to drain(s) number sufficient to allow water to thoroughly
evacuate the membrane surface. ·
All
penetrations shall be encased in concrete. Penetrations must be solid grouted
in place. No flexible pipe or corrugated pipe of any type shall be used for a
through slab penetration. Penetrations shall be spaced a minimum of 5 cm
apart to allow for detail work around penetration. ·
Examine
surface to be waterproofed for form tie holes and structural defects such as
honeycombing, rock pockets, faulty construction joints and cracks. Such
defects should be repaired in accordance to the following procedure. ·
In
case of highly damaged / cracked / weak substrates and construction joints, a
site engineered epoxy mortar should be prepared by mixing 3 part of Magnum Primer
Hardener Part A: 1 Part of Epoxy primer resin: 3.5 -4 Parts of Silica Sand to
repair holes, honeycombing, construction joints etc. ·
If
only surface cracks and moving cracks are encountered, the procedure to
repair them is covered under sections 3 and 4 below. ·
Active
water ingresses / leaks, should be protected ensure no water is spilled over
the surface to be treated prior to application Repair of Surface Cracks < 1.0 mm ·
Surface
cracks greater than 0.3mm and less than 1.0 mm width can simply be coated
with two coats of Smartcare PU Magnum US sandwiched 60 Gsm non-woven geotextile,
the coating extended to 75 mm on either side of the crack. ·
Opening the cracks
which is less than 1mm, if any, in V/U shape using electrically operated
cutting machine. Cleaning the surface thoroughly from dust and loose
particles using wire brush and air blower. The same shall be sealed/filled
with SBR mortar admixed with AP SC Multipurpose polymer/Repair Polymer at the
ratio of 1:3:5%(Cement + sand + 5% polymer of Asian Paints Multi-Purpose
polymer or equivalent) and pre stripping the cracks with 40 gsm geofabric/40
gsm fiber mesh with AP SC PU Magnum US by extending 50 mm on both the sides
of crack. ·
Apply
epoxy primer and after drying, minimum Two coats of Smartcare PU Magnum US
sandwiched with 60 gsm non-woven geotextile, the coating extended to 75 mm on
either side of the crack. Repair of Surface Cracks > 1.0 mm and
Construction Joints ·
Wider
cracks (> 1.0 mm) should be routed out to 6 mm wide by 12 mm deep. ·
Clean
the groove using water jet / air blower to remove dust, dirt etc, ·
If
any crack found more than 1mm then treatment shall be done with Low viscous
epoxy grouting (same shall be paid separately) and pre stripping the cracks
with 40 gsm geofabric/40 gsm fiber mesh with AP SC PU Magnum US by extending
50 mm on both the sides of crack Repair of Moving/Dynamic Cracks: ·
Chip out & Remove the old filler
material from the affected area. ·
Clean the surface with the help of air
blower to remove the dust and loose particles. ·
The sausage should be inserted in hand
operated application gun and nominal pressure has to be applied over the
trigger of the gun so that sealant starts extruding out of the nozzle &
filled in the joints. A slightly excess amount to be applied for tooling and
finishing purpose. ·
Spread at edges to ensure adhesion of
sealant at both edges of joint/ crack and then level the sealant with
spatula/ putty knife. ·
Allow the sealant to cure for 24 hours to
achieve its full strength. ·
Clean and wipe the existing coating with
solvent (Xylene/Acetone) 75mm either sides of crack. ·
Apply epoxy primer, after drying time
apply minimum Two coats of SmartCare PU Magnum US at a dosage of 0.750 – 0.80
Kg/Sqm/coat, sandwiched with wet/dipped 60 GSM non-woven geotextile/EPDM
Tape, fixing and application of coating shall be extended to 100 mm on either
side of the crack. ·
Step 1 – After solvent cleaning Apply a
coat on the existing coating extended 75-80 mm both the sides of cracks. ·
Step 2 – Dip the 100/150 mm wide tape
into the mixed solution bucket. ·
Step 3– Fix the geotextile/epdm fleece
snugly & uniformly impregnates on the wet coating extended has to be
stretched at both sides in equal width. ·
Step 4 – Apply one more coat of PU Magnum
US over it at a dosage of 0.75-0.80 kg/Sqm extended 100 mm at both sides to
fully encapsulate the membrane in the coating. Treatment of Construction Joints / Change of Planes
(With SC AP GP Grout) SURFACE PREPARATION: ·
Clean the substrate surface and
remove loose concrete, dust, oil, paint, grease, waterproof coating etc. If
the concrete surface is defective or has laitance, it must be cut back to a
sound base. The old concrete substrate should be saturated with clean potable
water for several hours. Make sure before SmartCare GP Grout/Micro concrete
is poured, free water from the surface and the formwork must be removed.
Apply bonding agent if required. MIXING ·
A pan mixer should be used so
that a homogeneous concrete mix is obtained. Charge approx. 80% of the total
required water i.e. 2.6 - 3 litres to pan mixer, start addition of powder
slowly under continuous mixing. After complete addition of powder, check the
flow and add remaining 20% water i.e. 0.65-0.75 litres (Note – Check for
bleeding, if bleeding occurs over all water content has to be reduced) and
mix for 2-3 minutes to get a homogeneous free flowing, uniform & lump
free mix. Total water required: 3.25 to 3.75 litres per 25 kg bag i.e.,
14+/-1% of the weight of powder. Make sure that for a 25 kg bag volume of
water should not exceed 3.75 litres. Water that is added should be clean and
potable. PLACING ·
Pour the homogeneous mixture of SmartCare
GP Grout/Micro concrete into a watertight shuttering. Post removal of the
formwork cure the repaired concrete for minimum 5- 7 days by sprinkling water
regularly. ·
Allow the fillet/groove material to dry,
after drying apply epoxy primer and then after drying time, 2 coats of Smartcare PU Magnumn US to a minimum
band width of 150mm to a consumption of minimum 1.6 kg/sqm in two coats and
embedding 60 Gsm Geotextile Fabric in between the coats, prior to coating of
entire area. COVING/WATTA: ·
Providing and laying Angle fillet/Coving 75mm
x 75mm at all vertical/horizontal junctions with 1:4 Cement/Sand mortar
admixed with SmartCare Repair polymer
@ 5 kg per 50kg bag of cement. (Mixing ratio for Coving: 1 cement: 4 Sand:
0.1 Repair polymer). ·
And pre-stripping to be done with 60 Gsm non-woven
geo-textile with applying 2 coats SC Ultra Block 2k in both horizontal and
vertical junctions in the tanks or equivalent coating. EXPOSED REINFORCEMENT TREATMENT:
·
Should be treatment with non-shrink
grout Asian Paints General Purpose Grout by cutting the exposed rod up to
15-20mm down, apply bond coat with Cement-Polymer slurry and then fill the
same with grout material. BORE PACKING:
·
Core cut holes, cut out area, filtration plant etc., must
be grouted with non-shrink cementitious grouts before the waterproofing
coating is taken up for application. ·
Before the bore packing, surface of the PVC /MS pipe and
concrete surface will be made rough and sand will be sprinkled with polymer
bonding agent Smartcare Multipurpose polymer admixed with cement @ 1:1. ·
After 10-15min when bond coat is in wet condition fill
non-shrink Smartcare General Purpose Grout admixed with 0.15 W/P ratio for
25Kg bag. ·
Further the treatment shall be covered into the coating
with prestripping. APPLICATION
OF THE PRIMER: ·
Components
A (resin) and B (hardener) are packed in two separate containers, having the
correct predetermined mixing ratio by weight. The whole quantity of component
B is added into component A. The two components should be mixed for about 2-3
minutes with a low-speed mixer (300 rpm), until the mixture becomes uniform. It
is important to stir the mixture thoroughly near the sides and bottom of the
container, to achieve uniform dispersion of the hardener. Then add equal
quantity of water (30% by weight of primer) and continue mixing to ensure
that the mixture obtains the desired workability ·
Apply
the product using a Roller @ 200 - 400 Gms/Sq.m consumption. If the substrate
is porous apply a second coat of primer after 4 hours and before 6 hours of 1st
application coating. APPLICATION
OF THE SMARTCARE PU Ultron: (2.25 Kg/Sq.m for 3 coats for 1.5mm DFT) ·
The drum
component should be mixed for about 3-5 minutes with a low-speed mixer (300
rpm), until the mixture becomes uniform. It is important to stir the mixture
thoroughly near the sides and bottom of the container, to achieve uniform
dispersion of the hardener. ·
Check
the moisture of Surface to be coated, the moisture content of substrate
should be < 4%. ·
Apply
1st coat of Smartcare PU Ultron using a roller or airless spray @
a consumption of 0.8 Kg/Sq.m on primed substrate. ·
After
6 hours and within 12 hours of 1st coat application of Smartcare PU
Ultron, apply the second coat of Smartcare PU ultron using roller or airless
spray @ a consumption of 0.80 Kg/Sq.m ·
After
6 hours and within 12 hours of 1st coat application of Smartcare
PU ultron, apply the second coat of Smartcare PU Ultron using roller or
airless spray @ a consumption of 0.70 Kg/Sq.m APPLICATION
OF THE SMARTCARE PU Ultron AT DAY LAPPING JOINTS: ·
Where
a new waterproofing of Smartcare Ultron is joint to previous day coating of
Smartcare PU Ultron at day joints, a new application will be lapped into
existing by minimum 100-150 mm. ·
Where
existing cured membrane of Smartcare PU Ultron is done 24 hours prior or
surface is contaminated by dust, dirt etc, minimum 100-150 mm of Lapped end
will be cleaned using cleaning agent – Acetone or Xylene solvent. ·
Allow
the surface to dry and after that apply Smartcare PU Ultron as per procedure
listed in Section: application of Smartcare PU Ultron. TERMINATION: ·
Termination shall end after Floor Finish Level + 400 mm minimum. ·
Vertical: Enveloping system over parapet wall
and terminating the coating into a groove of 5mm x 5mm. The groove will be
sealed by using sealant / Epoxy mortar depending upon site requirements. CURING: ·
Allow
the SmartCare PU Ultron to cure to a firm rubber, [Min. 24 hours at 23 °C,
50% RH], the coating achieves full cure in 2-3 days. SPRAY POLYURETHANE FOAM APPLICATION SC PU INSULATOR: ·
The spray polyurethane foam
components (A) and (B) shall be processed in accordance with the
manufacturer’s instructions. ·
The polyurethane foam shall be
sprayed within the manufacturer's guidelines for temperature, humidity, and
other atmospheric conditions please refer PIS. ·
The polyurethane foam shall be
sprayed in minimum 1/2-inch-thick passes (lifts) with the overall thickness
to be a minimum of 40 mm. The full thickness of spray polyurethane foam to be
applied with any given area in same day. ·
Moisture Level for SmartCare SPUF application to be less than 4%. INSULATION: ·
Application of SmartCare PU
Insulator shall be sprayed in two components (a polyol and an isocyanate)
that when mixed expand their volume to form a seamless layer. Within minutes
this foam can be walked on and cures to 90% of its full strength in 4 hours. ·
It is better to apply in two-three
layers to achieve desired thickness of Avg.50mm on horizontal surface only.
Try and achieve Initial layer thickness 1.5-2.5 cm to achieve good adhesion. ·
It shall be done only for
horizontal surface. KEY
CHECKS BEFORE PU INSULATOR: ·
Surface temperature range for PU
spray foam application shall be 12 – 40 Degrees (Check with temperature
sensor). ·
Wind speed should be not more than 30
Km/h. ·
Minimum thickness: 40 mm. PROTECTION:
PU Magnum US ·
Components
A (resin) and B (hardener) are packed in two separate containers, having the
correct predetermined mixing ratio by weight. The whole quantity of component
B is added into component A. The two components should be mixed for about 2-3
minutes with a low-speed mixer (300 rpm), until the mixture becomes uniform. It
is important to stir the mixture thoroughly near the sides and bottom of the
container, to achieve uniform dispersion of the hardener. Then add equal
quantity of water (30% by weight of primer) and continue mixing to ensure
that the mixture obtains the desired workability ·
Apply
the product using a Roller @ 200 - 400 Gms/Sq.m consumption. If the substrate
is porous apply a second coat of primer after 4 hours and before 6 hours of 1st
application coating. APPLICATION
OF THE SMARTCARE PU Magnum US : (1.6 Kg/Sq.m for 2 coats for 1.2 mm DFT) ·
The drum
component should be mixed for about 3-5 minutes with a low-speed mixer (300
rpm), until the mixture becomes uniform. It is important to stir the mixture
thoroughly near the sides and bottom of the container, to achieve uniform
dispersion of the hardener. ·
Check
the moisture of Surface to be coated, the moisture content of substrate
should be < 4%. ·
Apply
1st coat of Smartcare PU Magnum US using a roller or airless spray
@ a consumption of 0.8 Kg/Sq.m on primed substrate. ·
After
6 hours and within 12 hours of 1st coat application of Smartcare
PU Magnum US, apply the second coat of Smartcare PU Magnum US using roller or
airless spray @ a consumption of 0.80 Kg/Sq.m . Application Process for Vertical surface – Step 1 – Epoxy base primer ·
The drum
component should be mixed for about 3-5 minutes with a low-speed mixer (300
rpm), until the mixture becomes uniform. It is important to stir the mixture
thoroughly near the sides and bottom of the container, to achieve uniform
dispersion of the hardener. ·
Check
the moisture of Surface to be coated, the moisture content of substrate
should be < 4%. ·
Apply
1st coat of Smartcare PU Magnum US using a roller or airless spray
@ a consumption of 0.8 Kg/Sq.m on primed substrate. . Consumption
: 1.6kg/sqm PRECAUTIONS Do not apply during rains or extreme temperatures. Avoid abuses which may lead to puncturing of membrane.
Ensure that the product is applied at least 6
inches inside the drain pipe. For best results, apply parapet to
parapet to envelope the entire building. Protection System: ·
After drying of the coating, the same
shall be covered with Non-Woven geotextile sheet of 200-250 GSM as a
separation layer followed by PCC screed to slope.
·
The screed shall be further divided into panels of
4m X 4m with 10mm wide and 25mm deep control grooves, the same shall be
filled with backer rod followed by filling of SmartCare Hybrid PU Sealant. ·
Make angle fillets all around the periphery
of the wall and pedestals (if any) with polymer modified mortar with required
curing. . |
8.0 COVERAGE / CONSUMPTION |
Epoxy Primer: 200-400 Gms/Sq.m PU Ultron : 2.3
Kg/sq.m (minimum two coats recommended). PU Insulator: 3 Kg/Sq.m (minimum two – three coats
recommended to achieve required thickness). PU Magnum US : 1.6 kg/sqm |
9.0 CLEAN UP |
Clean up tools and machinery using recommended
solvent. |
10.0 QUALITY OF APPLICATION |
The applicator shall conform to all precautions and
quality control systems to ensure correct application of the material in
question. These include:
For any further clarifications / assistance please
contact local team Methodology will change based on site condition and after
manufacturer approval. |
Comments
Post a Comment
want to learn more or want any ebooks let me know