Process of Microcontrete Flooring

Image
Process of Microcontrete Flooring  Process On Tile/Marble Flooring  1 Sand The floor with Metal Grinder & Metal Diamond Wheel.  2 Clean the surface ensuring there is no dust on the surface  3 Apply 1 coat of Colortek Neogrip – F primer in thin layer – no dilution required  4 Let dry for 8 hrs  Application Process for Base & Topcoat   1. Apply 1st base coat of  base coat, polymer 3kgs, water 1 kgs, base coat filler 12  kgs mix it well until all lumps are dissolved and it becomes a smooth paste. (3:1  IS RATIO FOR POLUYMER AND WATER MIXING. 4:1 IS RATION FOR POLYMER  WATER MIX WITH POWDER  2. Apply in the thickness of 1-2 mm so that it gives you a coverage of 155 sqft  approx..  3. Let dry for 1 day  4. Sandin to be done by 30# grit resin pad – 8mm thick , Dcrf 7u – then sand with  60# grit resin pad – 3mm  5. Apply – 2 coats of polymer primer by diluting with water 1:1 ratio (1kgs polymer...